The business need for the project.-the project charter includes the business need for the project. the project charter is
created during initiating process group and signed by senior management. the project
charter is a high-level document that identifies the project manager, the product
description, and a description of the business need for the project.
the project charter does not include a wbs. a work breakdown structure (wbs) provides
a detailed breakdown of the deliverables of a project. the project charter is a high-level
document that does not include project details.
these details are identified during the planning process group, after the initiating
process group is complete and the project charter has been created.
the project charter does not include a scope statement. the scope statement is created
during scope definition process of the planning process group, after the initiating
process group is complete and the project charter has been created.
although the project charter may contain some schedule information, such as a summary
milestone schedule, it does not contain a definitive project schedule. a definitive project
schedule is an output of the schedule development process, which is a part of the
planning process group.