Does the new Spring length need to be agreed by the Product Owner if a SCRUM Team decide to revise it?

Does the new Spring length need to be agreed by the Product Owner if a SCRUM Team decide to revise it?

Change Image    Delete



Asked by Bthiede, Last updated: Jan 09, 2025

+ Answer
Request
Question menu
Vote up Vote down

2 Answers

inb.soumahu

inb.soumahu

inb.soumahu
In a Retrospective, a Scrum Team decides to revise the Sprint length. The new Sprint length needs to be agreed by Product Owner.

I think the answer should be No. Because the questions says ".... a Scrum Team decides.....". TheProduct is part of a Scrum Team, so if a Scrum Team decides he/she (Product Owner) already agreed! So it is not necessary to have an "extra" agreed from the Product Owner.
upvote downvote
Reply 

John Smith

John Smith

John Smith
John Smith

Answered Nov 04, 2016

Yes

The Product Owner needs to ensure that it is short enough to limit business risks and also short enough so the team can synchronize the development work with other business events. Please note that the finalized Sprint Length cannot be longer than 1 calendar month. Correct answer is A
upvote downvote
Reply 

Advertisement
Advertisement
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader

Email Sent
We have sent an email to your address "" with instructions to reset your password.