What happens when a Sprint is cancelled? Select three. If part of the work is potentially releasable, the Product Owner typically accepts it At the Sprint Retrospective the Scrum Master determines who from the Development Team is responsible for cancelling the Sprint
When a Sprint is cancelled, any completed and Done Product Backlog items are reviewed. If part of the work is potentially releasable, the Product
Owner typically accepts it. All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog.